While, the Billerud mills carry out continuous maintenance of capacity during ongoing production, there is also a reoccurring need for a period of more extensive maintenance during a year. To provide for this extensive maintenance the mills shut down pulp production i.e. a maintenance stop. The time period for a maintenance stop is therefore defined as the number of day with zero pulp production.
Information on the planned maintenance stops are shown in the table below. Maintenance stops at Beetham have an insignificant effect on Billerud's overall earnings.
| Year |
Mill |
Period |
Quarter |
Days |
| 2010 |
Gruvön Karlsborg Skärblacka |
|
2 3 3
|
10 10 8
|
| 2009 |
Gruvön Karlsborg Skärblacka |
No major stop in 2009
|
3 3
|
10 8 |
| 2008 |
Gruvön Karlsborg Skärblacka Beetham |
20-26 October 19-28 August 14-21 April 27 July - 9 August |
4 3 2 3 |
7 10 8 13 |
| 2007 |
Gruvön Karlsborg Skärblacka Beetham |
16-24 April 21-27 August 7-14 May 16-27 July |
2 3 2 3 |
8 7 7 24 |
| 2006 |
Gruvön Karlsborg Skärblacka Beetham |
no major stop 22-29 August 25 mars - 1 April 17-30 July |
- 3 1 3 |
0 8 5 14 |
| 2005 |
Gruvön Karlsborg Skärblacka Beetham |
16-26 September 23-29 August 16-23 april 17-31 July |
3 3 2 3 |
8 7 7 14 |
| 2004 |
Gruvön Karlsborg Skärblacka Beetham |
16-17 April 24-31 August 8-16 May
|
2 3 2 |
11 7 8 0 |
| 2003 |
Gruvön Karlsborg Skärblacka Beetham |
20 August - 4 September 6-16 May 22-30 March
|
3 2 1 |
5 10 8 0 |
| 2002 |
Gruvön Karlsborg Skärblacka Beetham |
19-26 October 27 August - 3 September 13-21 april |
4 3 1
|
7 7 8 0 |
| 2001 |
Gruvön Karlsborg Skärblacka Beetham |
8-17 September 21-28 August 5-15 May |
3 3 2
|
9 7 10 0 |
| Mill |
Product area |
Pulp capacity |
| Gruvön |
Kraft paper, containerboard |
685 000 |
| Karlsborg |
Kraft paper |
290 000 |
| Skärblacka |
Kraft paper, containerboard |
400 000 |
| Beetham |
Kraft paper |
nm |